(1) Pre-Installation Checks Verify the model, parameters, and component completeness. Review the technical manual before installation.
For horizontal pumps, use a two-stage grouting method. Ensure: Centerline alignment with the foundation (±2 mm tolerance). Levelness within 0.1/1000. Coupling Alignment Methods: Straightedge and Feeler Gauge:Máx. misalignment <000000>le; 0.10 mm. Dial Indicator:Runout <000000>le; 0.15 mm; gap variance <000000>le; 0.10 mm. For belt-driven units, maintain parallel shaft alignment via pulley adjustment.
Inlet Pipe:Match or slightly exceed pump inlet size to prevent cavitation/sedimentation. Include a gate valve and expansion joint. Outlet Pipe:Match pump outlet size. Install a gate valve and pressure gauge upstream of the first valve. Key Rule:Throttle flow only at the outlet—never the inlet—to avoid cavitation.
For mechanical seals, connect water lines per manual (pressure gauge side = inlet). Grease-lubricated bearings require no cooling water.
Bookmark
Daniel Féau processes personal data in order to optimise communication with our sales leads, our future clients and our established clients.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.