EUR
en
Its steel flues are protected with Pennguard linings
The East Kentucky Power Cooperative (EKPC) produces electricity for 16 regional power cooperatives. They serve one million consumers in 89 counties. The Spurlock Power Station near Maysville, Kentucky is EKPC’s largest power station. Spurlock station has recently completed two wet limestone flue gas desulphurization (FGD) systems, each with a new, PennguardTM lined industrial stack.
The two FGD systems were fitted to the 325 MW Unit 1 (in service since 1977) and the 525 MW Unit 2 (in service since 1981). Both are conventional coal fired units, using coal with a sulphur content of 3.5 % – 4.2 %. The two FGD’s will remove some 98 % of the sulphur oxides from the exhaust gas flows of Units 1 and 2. In addition to Units 1 and 2, the Spurlock station operates two 268 MW circulating fluidized bed (CFB) boilers. They are among the cleanest coal fired units in the United States.
The addition of FGD systems to Units 1 and 2 presented EKPC with several options for the industrial stacks. EKPC looked at the possibility of relining the existing Unit 2 industrial stack. This to make it suitable for carrying FGD treated, water saturated flue gas.
The fast construction and commissioning schedule of the FGD retrofit project however would not allow a sufficiently long outage to achieve this.
Therefore EKPC decided to award to Karrena International LLC the design and construction of two, 198 m high concrete industrial stacks. Each stack has a single, Pennguard TM lined steel flue.
Karrena International decided that they would build, grit blast and primer coat steel flue sections on ground level. This was based on the project time schedule and the weather conditions in Kentucky. These steel flue sections were welded together in the windshield. Then the Pennguard TM lining was applied in the erected flue, using a movable work platform.
A team of up to three Hadek Quality Assurance (QA) Inspectors was present on site during the surface preparation and lining installation process. Hadek Protective Systems has a group of 14 Quality Assurance Inspectors who are trained to supervise the complete field installation process of a Pennguard TM lining.
These pages show some pictures of the process of constructing and lining the Spurlock steel chimney flues.
The steel flue diameter of the Unit 1 industrial stack is 6.40 metres. The Unit 2 steel flue is 8.24 metres in diameter. Karrena decided to pre-fabricate steel flue sections on site, close to the new chimneys. The grit blasting required for the Pennguard TM Block Lining System, as well as the application of Pennguard TM Block Primer, were also performed on ground level.
Once grit blasted and primer coated, the steel flue sections were carried to the industrial stack with a mobile crane. The sections were then attached to the flue in the industrial stack by welding from two sides. The welds were cleaned with power brushes and then hand painted with Pennguard TM Block Primer.
With flue erection complete, Karrena installed a full size suspended work platform to facilitate the installation of the Pennguard TM lining system. The platform accommodated a team of up to 10 installers and support workers, who applied the Pennguard TM lining from the bottom to the top of each flue. A smaller, faster lift moving through a hatch in the center of the platform was used for transportation of the installation crew, their tools and the Pennguard TM lining materials. The lining of the 162 m tall Unit 1 flue took 45 days and the lining of the 165 m tall Unit 2 flue took 38 days.
Mixing of the two component Pennguard TM Adhesive Membrane is a critical step in the application process. For the Spurlock project, Karrena used two of Hadek’s proprietary, automated mixing machines. In order to track the quality of the mixing process on a pail-by-pail basis, the staff in charge of the mixing machines produce a small sample card for each pail. Hadek’s QA Inspectors will systematically check the curing of the adhesive on the cards, as a first confirmation that mixing has been successful.
On the work platform, the installers apply the Pennguard TM lining using a double buttering technique while minimizing any air inclusion. The installers apply the adhesive back and side joints at the required 3 mm thickness. The application process is monitored by Hadek QA Inspectors, who also keep track of temperature and humidity at regular intervals. The two steel flues in the Unit 1 and Unit 2 wet stacks have a combined surface of 8,130 m².
For any power station owner, fire is one of the more serious risks both during the construction of new plant and during operation and maintenance of existing equipment. FGD plants and the chimneys built directly next to FGD plants are no exception. Ever since the introduction of FGD, a number of large fires have occurred in FGD plants in North America, Europe and Asia.
At Hadek’s request, the Thermal Sciences group of the Exponent engineering company have performed a study entitled “Performance of Different Chimney Flue Designs During Large Power Plant Fires”.
Exponent’s study report shows how Pennguard TM lined steel chimney flues are effectively insulated from overheating, as they are filled with extremely hot smoke from an FGD or power plant fire. By comparison, steel flues without a Pennguard TM lining or FRP flues are more likely to overheat, catch fire and collapse (study report is available on request).
Exponent’s test work also included a fire propagation test, to see how a fire could escalate if the joints between Pennguard TM Blocks are accidentally set on fire. The test showed that although the joint will catch fire, it will burn slowly and has a tendency to extinguish by itself after some minutes.
The Exponent study shows that although good fire safety practice still has to be followed during construction and operation, the use of Pennguard TM lined chimney flues is a valuable, additional step in improving power plant fire safety.
Bookmark
Daniel Féau processes personal data in order to optimise communication with our sales leads, our future clients and our established clients.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.