EUR
en
Surface water on construction sites can come from rain, runoff or nearby bodies of water, such as ponds, lakes or rivers, along with other areas impacted by rainfall. The primary challenges associated with surface dewatering include:
Groundwater dewatering focuses on removing water from under the earth’s surface. Challenges here include:
Effective surface water management is essential to prevent delays, protect structures, ensure worker safety and not incur unforeseen costs.
Groundwater presents different challenges that often require more complex systems to lower the water table and keep excavations dry.
With sustained winds exceeding 150 mph and more than 30 inches of rain falling, Hurricane Maria tore a path of destruction through Puerto Rico in September 2017, leaving an island of people in fear of catastrophic flooding. In the aftermath of the storm, it was immediately clear there was a significant issue with the Guajataca Dam. The dam’s spillway began to collapse, and its valves were destroyed, causing an outpouring of water that resulted in major erosion and necessitated the evacuation of 70,000 homes. There was also a tremendous fear the dam could fail and flood homes downstream.
The U.S. Army Corps of Engineers began mobilizing teams to help save the community. In less than 24 hours, a Thompson Pump team was on the ground. The team determined 10 complete systems consisting of 18-inch centrifugal pumps would be needed, due to their automatic self-priming, flows up to 11,000 GPM, heads up to 130 feet, suction lifts up to 28 feet and large solids handling up to four inches.
The pumps were placed and began lowering the dam’s water level, thus alleviating the possibility of major flooding. The team then went a step further and used the pump systems to reroute water from the dam’s reservoir to a canal feeding three water treatment plants. This allowed clean water to be made available to the community for the first time in weeks.
For more than a year, the pump systems continued to operate, allowing the community to recover and rebuild, and perform hurricane mitigation to prevent any future flooding issues.
In one of the largest dewatering projects west of the Mississippi River in 2020, immediate work was needed to remove and replace failed culvers running underneath the 10,100-foot operational length main runway at Joint Base Lewis-McChord Airfield. To replace the two original 12-foot diameter steel culverts, crews needed to place the footers and other supports about 10 feet under the water table of Clover Creek, which meant the entire area needed to be dewatered.
The U.S. Army Corps of Engineers Seattle District worked with a local dewatering subcontractor to design a dewatering system to temporarily lower the groundwater so the culvert removal and replacement could be completed. 12-inch rotary wellpoint pumps were selected due to their unique performance capabilities, having been specifically designed and engineered for wellpoint and sock dewatering with maximum discharge flows of up to 2,500 gallons per minute, air handling capabilities of up to 400 cubic feet per minute and high-vacuum capability of up to 29-inch Hg.
The system was so efficient it lowered the water table and held the excavation open for six months, allowing all reinforcements to be installed at once.
Managing dewatering on construction sites requires understanding the specific challenges posed by surface water and groundwater and choosing the right combination of methods and equipment tailored to each challenge. By addressing these factors, construction projects can achieve efficient water management and ensure a safe, efficient and productive construction environment.
Bookmark
Daniel Féau processes personal data in order to optimise communication with our sales leads, our future clients and our established clients.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.